Thanks, we'll try and post some more "exciting" pictures as things progressLooking good Ryan B)
Amazing stuff. Feels great to colo at Colo@.
That's awesome Brand new generator, good to go!08/21/2013
A ton of materials have arrived, pipe bending equipment to bend the 4" conduit for power runs, fuel-oil piping being installed and just a few pictures of the generator replacement that was previously done as well as 2 pictures of our overhead busway that is used in all our power deployments that allows flexible circuit delivery to cabinets form 10A 120v to 30A 3-Phase.
Our crash carts are all wide screen! 21" or better, lol
It's an 80 cabinet expansion within the existing space on our 4th floor of 34 Peachtree, just a build out of more cooling a power capacity. This includes the addition of another 500kw power system and N+1 heat rejection units into a 2nd floor space that is ambient, which adjoins our 2nd floor offices.Pretty rendering
How many square feet of space is this upgrade/build?
Agreed, this is pretty awesomeThat is awesome! The datacenter looks very nice! Can't wait to see updates
Agreed, this is pretty awesome
Yes. Three hours didn't cut it. Fixed my wrong choice of wording.Obligation = objection MannDude likes sleep ,that rare treat.
The post needs keyword tagging too.
Existing overhead delivery. Additionally raised flooring and trying to use pressure to "push" cold air up, is inefficient. Why fight the natural flow of air?Just out of interest, is there a reason you're going top down instead of bottom up?